West Huntspill Water Recycling Centre
Envolve operate at the Strategic Partner level within the Wessex Water AMP 6 Delivery programme.
Location: West Huntspill, Somerset
Project Type: Bathing Water Improvements
Client: Wessex Water
Project Duration: 100 weeks
Contract Value: £5m
Taunton Ham WRC
The Taunton Ham WRC Advanced Digestion scheme formed part of this programme and was generated by the Wessex Water output of producing more renewable energy.
Location: Taunton, Somerset
Project Type: Environmental
Client: Wessex Water
Project Duration: 64 weeks
Contract Value: £4m
Frome Valley
The Frome Valley Relief Sewer scheme represents a £15million capital investment by Wessex Water.
Location: Frome
Project Type: Relief Sewer
Client: Wessex Water
Project Duration: 52 weeks
Contract Value: £8m
Chippenham Gateway Sewer Requisition
Wessex Water were served under S98 of the Water Industry Act to provide an offsite foul water connection for St Modwen’s new Chippenham Gateway development.
Location: Chippenham
Project Type: Sewer Requisition
Client: Wessex Water Services Ltd
Project Duration: 30 weeks
Contract Value: >£2m
Bristol Road SPS
The Bristol Rd scheme was the largest of 12 projects to improve the bathing water quality at Burnham-On- Sea.
Location: Bridgwater
Project Type: Shafts
Client: Wessex Water
Project Duration: 15 months
Contract Value: £4.5m
Bicester STW Growth
The Bicester STW Growth scheme was driven by the projected increase in population in the Bicester STW catchment area.
Location: Bicester, Oxon
Project Type: Waste Water Treatment
Client: MWH Treatment, Thames Water
Contract Length: 6 months
Contract Value: £2.5m